
CLIENT CASE 1
CLYDEBANK RETAINING WALL
Clydebank
Railway Station, near Glasgow is situated on an elevated section
of electrified railway which is supported by a series of bridges,
retaining walls and embankments. When it became apparent that
the existing dilapidated brickwork retaining wall supporting
the rear of Platform No 2 was displaying signs of lateral movement
leading to localised subsidence to the platform surface, Network
Rail procured the services of a leading structural designer
to design a new retaining structure.
Following
approval of the final design, CK Contracts Ltd were contracted
to construct a new 50m long x 2.4m high x 1.34m thick solid
core Class B brickwork retaining wall offset from the existing
wall by 2 metres. Following construction, the new wall was to
be backfilled with granular material against the existing wall
to arrest any further lateral movement. The design allowed for
the new wall to be constructed during normal working hours without
the need for railway possessions or isolations. Because of the
close proximity of the existing wall, temporary structural raking
props were installed prior to construction commencing in order
to maintain the wall’s stability during the deep excavations
required.
The site was located within a narrow strip of sloping ground
situated between the rear of Platform 2 and the gable wall of
an existing tenement building and could only be accessed from
one end. A temporary access road was required to be ‘cut
through’ the existing embankment to allow the site to
be serviced with plant and materials. Due to the restricted
nature of the site, the access road required to be formed over
an area of the proposed wall’s footprint. Consequently,
it was necessary to carry out the works in three phases, with
each phase requiring to be completed in its entirety prior to
removing the associated section of access road and retreating
along the site to the subsequent phase.
During the initial phase of the works, the existing embankment
ground levels combined with the steep embankment slope gradients
prohibited the installation of a founded retaining wall and
forced a change of design. CK Contracts Ltd put forward an alternative
design solution in the form of a 1.5m high gabion wall installed
along an 8m section of the embankment toe, backfilled to the
crest of the embankment with granular fill. This alternative
design was adopted and successfully constructed.
The new retaining wall, constructed during phase 2 & phase
3, was formed using 35,000 Class B engineering bricks constructed
on top of a 500mm deep x 1750mm reinforced concrete foundation,
complete with and 850mm deep toe beam, all of which was cast
into the existing embankment slope. The foundation was stepped
at two locations in order to negotiate the geometry of a step-out
in the exiting wall. Drainage to the rear of the new wall was
provided via of sloping weep pipes installed at 2m centres combined
with a 150mm diameter slotted pipe out-falling to a formed granular
soakaway.
The
entire project was successfully completed within an agreed 10
week programme and delivered within the tendered contract sum.
Back