General Construction Concrete / Masonry Repairs Roughcasting General Groundworks Hire of Specialist Labour Rail Division
   
  C.K. HOME
  C.K. BACKGROUND
  C.K. SERVICES
  C.K. TESTIMONIALS
  C.K. CONTACT DETAILS
 
CK Contracts Ltd
 
Rail Division
Falkirk Swing Bridge

CLIENT CASE 1
FALKIRK SWING BRIDGE
BRIDGE DECK RENEWAL

Falkirk Swing Bridge is located within the town of Falkirk and carries the Scottish Central railway line over the Forth & Clyde Canal between Carmuirs West Junction and Falkirk Grahamston. The permanent way over the structure was provided by baseplates screwed into longitudinal timber waybeams but over the years problems with track gauge spread and derailments required that improvement works to the permanent way construction be effected.

Following an extensive design process it was decided that a load bearing timber bridge deck would be installed onto which ballasted track would then be laid. The repair scheme firstly required modifications to be carried out to the existing steel superstructure in order that the structure could accept the new deck timbers. These enabling works were carried out during a series of track possessions in advance of the main redecking operation. The redecking works would be carried out during a 54 hour possession together with p-way / waybeam removal, deck waterproofing and p-way relaying.

The production of site sizes collected by the scheme designer, allowed the new deck timbers to be manufactured from greenheart hardwood timber to the exact sizes required to fit the structure, including notches to accommodate web stiffeners, curved sections to match perimeter beams etc. The availability of accurate survey information also allowed the timbers to be predrilled at the proposed fixing bolt locations in order to reduce site installation time.

CK Contracts Ltd were contracted by First Engineering Ltd to install the new hardwood timber deck which was scheduled to take place during a weekend track possession. On receipt of the new hardwood timbers from the sawmill, CK Contract Ltd carried out a successful pre-works trial erection of the complete timber deck to prove the fit prior to commencement of the site works.

Following removal of the existing permanent way, timber waybeams and walkway timbers, a steelwork contractor plated the top flange of the longitudinal rail bearer beams to raise them level with pre-installed ledge angles down either cess both of which would ultimately support the new deck.

The new deck timbers were individually numbered and grouped according to their location on the bridge. The timbers were delivered to the site by articulated lorries and transported to the bridge alongside the Forth and Clyde Canal via a purpose built steel trackway road. A 35T site crane was positioned at the end of the trackway road to transfer the timbers directly form the lorries onto the bridge ready for installation.

Installation of the timbers was carried out manually with each timber being positioned in accordance with the scheme plan by 6 men using 3 sets of log gabs. Each timber was secured using zinc plated steel ‘L’ bolts which were fitted through pre-drilled / countersunk holes onto the underside of the steelwork flanges and tightened using socket spanners. The complete deck was successfully installed during a 12 hour shift ready for a Wolfin IB waterproofing system to be overlaid.


Following the waterproofing operation, ballasted track was installed over the bridge deck incorporating steel sleepers and guard rails allowing the complete project to be returned ahead of possession.

------------------------------------------------------------------------------------
CLIENT CASES...

Falkirk   CASE 1 FALKIRK SWING BRIDGE BRIDGE DECK RENEWAL
Click here for details.
     
Lugton   CASE 2 LUGTON
Click here for details.
     
------------------------------------------------------------------------------------
 
General Construction
Concrete / Masonry Repairs
Roughcasting
General Groundworks
Hire of Specialist Labour
Rail Division

HOME / BACKGROUND / SERVICES / LATEST NEWS / CONTACT US
general construction / concrete repairs / roughcasting / general groundworks / hire of specialist labour / railway division

CK CONTRACTS LTD / LANGSTILLY FARM / LOCHWINNOCH / PA12 4DR / TEL: 01505 843603 / FAX: 01505 843624
EMAIL : ENQUIRIES@CKCONTRACTS.CO.UK
Hire of Specialist Labour